Sjukhusomrade Hospital
Malmo, Sweden

Project Scope:

The design, delivery and installation of the HVAC for 2 OR’s, 1x Preproom, (non) sterile (storage) rooms, central sterile room into Modulair building solution.

Project Data:

Duration: 6 months

Overview of deliveries and installations:
 

3 x Hybrid Max e3-09 DH, 9.000 m3/h AHU including TCP-IP control via Modbus


3 x Delivery and installation of reheaters and TCP-IP control system via ModBus AHU


1 x Delivery and installation of duct work including components


1 x Validation program
 

Highlights:
1st hybrid all-in-one Max.e DH AHU for Operation Theaters via air-to-air heatpump DX.


1st Hybrid all-in-one AHU in Sweden in combination with the Opragon system.


Delivery and installation of reheaters for the OR’s and prep-room controlled by AHU’s via Modbus

20200311_122959.jpg

About Us

We have a strong network which was built during 25 years experience working with air treatment solutions.  We build long-term business relationships by offering efficient, sustainable concepts and quality products.   

Contact Us

PROCEDENT BV

De Drie Kronen 31

1601 MT Enkhuizen
The Netherlands

+31 (0)85 065 3270

email:  info@procedent.nl

Social Links

  • LinkedIn Site
  • Twitter